History of the project and News


  • 12.05.2005:
    • Delivery of Project material
  • 06.05.2005:
    • Conclusion document frozen
    • Project material frozen
    • Test execution document frozen
    • User manual finished
    • User manual frozen
    • Writing of Conclusion Document begins
    • Project ends
  • 04.05.2005:
    • Implementation document check
    • Test execution document check
  • 03.05.2005:
    • Coding finished, including bug fixes.
    • Implementation document finished
    • Test execution document finished
  • 29.04.2005:
    • Monitoring meeting
  • 28.04.2005:
    • Coding finished for testing
    • Test execution begins
  • 27.04.2005:
    • Official Demo
  • 25.04.2005:
    • Test plan frozen
  • 22.04.2005:
    • Test plan review
  • 20.04.2005:
    • Program code review
    • Test plan review
  • 11.04.2005:
    • Implementation Documentation begins
    • Test planning begins
    • Testing begins
    • User manual documentation begins
  • 08.04.2005:
    • Monitoring meeting
  • 06.04.2005:
    • Design document frozen
  • 01.04.2005
    • Formal technical review of design document
  • 24.03.2005:
    • Design document finished
  • 23.03.2005:
    • Requirements document frozen
  • 18.03.2005:
    • Monitoring meeting
  • 16.03.2005:
    • Informal review of requirements document
  • 11.03.2005:
    • Programming begins
  • 09.03.2005:
    • Requirements document finished
  • 02.03.2005:
    • Second prototype review
  • 21.02.2005:
    • Design documentation started
  • 18.02.2005:
    • Monitoring meeting
  • 16.02.2005:
    • First prototype review
    • Project plan review
  • 10.02.2005:
    • Project plan finished
  • 28.01.2005:
    • Initial meeting with Customer
    • Project plan documentation started
    • Requirements documentation started
  • 27.01.2005:
    • Project begins